- Planning of qualification and validation under EU GMP Annex 15, changes through change control, and the site change as a variation under Regulation (EC) No 1234/2008.
We provide project leadership and PMO for plant and CAPEX projects and support transfers, with construction plan, qualification, validation and regulatory path in one schedule. Annex 15 requires life-cycle planning of qualification and validation; a plan without these steps shows an end date that batch release will not meet.
Overview
Project leadership and PMO in production, quality and supply · EU GMP Annex 15 · ICH Q10 · ICH Q9(R1) · Regulation (EC) No 1234/2008
Last updated: October 19, 2026
A GMP project is finished only when the first batch has been released. Until then, construction, qualification, validation and the regulatory path run with their own dependencies, and each of them can set the end date.
Industries
Services
Setting up a PMO with a steering committee, reporting cadence, risk register and dashboards for project cost and project status; open GMP items belong in the same report as schedule and cost. The quality unit needs a fixed role in it; ICH Q10 Section 2.1 (b)(3) calls for a timely and effective escalation process for quality issues.
How we work together
A plant, CAPEX or transfer project in a GMP environment is complete only when the first batch has been released. Until then the date depends on construction and commissioning, on qualification and validation under Annex 15 of the EU GMP Guide and on the regulatory path. Each of them can set the end date, and none of them is visible in the construction plan alone.
Annex 15 requires qualification and validation to be planned (No. 1.1) and states that for large and complex projects separate validation plans may enhance clarity (No. 1.6). The project plan references these plans and carries their steps as tasks with dependencies: URS, FAT and SAT, IQ, OQ and PQ, process validation and the approvals in between.
Annex 15 leaves open to whom qualification and validation personnel report. What it requires is appropriate quality oversight over the whole validation life cycle (No. 1.3). In a project this means the quality unit sits on the steering committee, and its review and approval times appear as tasks in the schedule, including for service provider protocols (No. 2.6).
During the project the design changes, and every change hits documents that already exist. Annex 15 Section 11 requires planned changes to be evaluated with quality risk management for their impact on validation, documentation and regulatory status. The project's change register therefore belongs with the site's change control.
A site change adds a path that the project does not control itself: for medicinal products the variation under Regulation (EC) No 1234/2008, for medical devices informing the notified body in advance of planned substantial changes to the quality management system under MDR Annex IX Section 2.4. Its timing belongs in the same plan as process validation.
For transfer projects, ICH Q10 names the goal itself: to transfer product and process knowledge between development and manufacturing or between sites, as the basis for the manufacturing process, control strategy and validation approach (Section 3.1.2). A transfer plan that only moves equipment and documents leaves this part open; in the PMO it is a work package of its own, with acceptance.
| Project type | What else the date of the first batch depends on | Regulation |
|---|---|---|
| New or retrofitted facility | Qualification from URS to PQ, process validation | EU GMP Annex 15, Sections 1 to 5 |
| CAPEX on existing equipment | Change control, requalification | EU GMP Annex 15, Sections 4 and 11 |
| Technology transfer | Knowledge transfer, validation at the receiving site | ICH Q10 Section 3.1.2, EU GMP Annex 15 |
| Site change | Variation or information to the notified body | Regulation (EC) No 1234/2008, MDR Annex IX Section 2.4 |
Our approach
Step
Result
Project Charter & Scope
Scope, objectives, budget frame, milestones and owners defined, including the regulatory consequences of the investment or site change.
Integrated Schedule
Construction, qualification, validation and the regulatory path in one plan with a critical path; project plan and validation plan reference each other.
Governance & PMO
Steering committee, reporting cadence, escalation paths and risk register in operation, with the quality unit at the decision table.
Execution & Change Control
Progress, cost and open GMP items tracked together, every design change routed through change control under Annex 15 Section 11.
Qualification, Validation & Submission
IQ, OQ, PQ and process validation completed, variation or notified body information submitted at the planned time.
Handover to Operations
First released batch, closed deviations, documentation handed over and an operation that runs on without the project organization.
Common pitfalls
Qualification and process validation sit in a second plan that nobody reconciles with the construction plan.
The date of the first batch is then an assumption. Annex 15 No. 1.1 requires these steps to be planned, and in the project they belong in the same schedule as tasks with dependencies.
The quality unit is called in only for protocol approval.
Annex 15 No. 1.3 requires quality oversight over the whole validation life cycle. If QA joins only at the end, its objections arise at the point where every correction hits the critical path.
Supplier and service provider protocols are scheduled without review time.
Under Annex 15 No. 2.6, personnel at the manufacturing site confirm suitability and compliance with internal procedures before such a protocol is approved. Without this task in the plan, IQ stalls although the equipment is installed.
Design changes are decided within the construction project and never reach change control.
Annex 15 No. 11.4 requires planned changes to be evaluated for their impact on validation and regulatory status. A change known only to construction and procurement leaves completed IQ and OQ documentation open to challenge and can surface at the inspection.
The status report shows schedule and budget but no open GMP items.
Deviations, pending protocol approvals and open questions on the submission then stay invisible until shortly before release. ICH Q10 calls for a timely and effective escalation process that raises quality issues to the appropriate levels of management (Section 2.1 (b)(3)); in a project it should run through the status report and the steering committee.
Supply Chain & Technical Operations
In a first call we assess your situation and say what needs clarifying first in your case. Without obligation, reply usually within one working day.
FAQ
Image notice: The images on this page were generated using artificial intelligence. They do not depict real people, places, or events.
Projects from this industry
Related insights
All insights →CAPEX Planning & Qualification →
URS, tendering, FAT and SAT for regulated production facilities
Production Transfer & Scale-Up →
Technology transfer between sites with variation strategy and PPQ
GMP Facility Qualification & CQV →
Qualification master plan and IQ, OQ, PQ in parallel with construction
Interim Management →
Project and specialist roles on an interim basis, with handover to operations
Change Management →
Change control for changes to validated facilities and processes