Manufacturing site for biochemical active ingredients with a single production line

OEE optimization at a manufacturing site for biochemical active ingredients whose single production line had reached its capacity limits. The goal was to make downtime losses transparent and to make better use of available production capacity.

The challenge

The situation

The manufacturing site had reached its capacity limits. Systematic OEE tracking was lacking, which resulted in a lack of transparency regarding downtime losses. Inefficient communication between the process teams and inadequate capacity planning aggravated the problem. Frequent production stoppages caused by time-consuming cleaning processes further disrupted operations. The main objectives were to optimize downtime-loss tracking, to improve communication between the teams, and to reduce cleaning times in order to minimize stoppages.

Our approach

What we delivered

01

Comprehensive planning of the entire development project through to market launch

02

Regular status reports and assessment of objective attainment

03

Weekly project meetings to steer the project team

04

Introduction of systematic downtime-loss tracking and optimization of capacity planning

05

Reduction of cleaning times and minimization of production stoppages

The outcome

Results & impact

10% lower production costs

Reduction of production costs by 10 percent through more efficient use of production capacity.

Increased capacity utilization

Higher capacity utilization through improved team coordination and task management.

20% lower project costs

Reduction of project costs by 20 percent within 12 months.

In summary

The optimization led to a 10 percent reduction in production costs and improved capacity utilization. Within 12 months, project costs were reduced by 20 percent.

Sources
  • https://theentourage.de/case-study/oee-optimierung-biochemische-produktion/ (live case study, accessed 2026-06-14)

Your project

A comparable project?

Briefly outline your situation. We'll respond with an initial assessment, usually within one business day.

Prefer direct? +39 02 8904 1000
info@theentourage.it

  • Reply usually within one working day
  • 4 offices: DE · CH · IT · US
  • 100% life sciences