Safety stock in pharmaceutical manufacturing: what has to be measured before the overhaul

Why safety stocks in pharmaceutical plants grow in steps, which eleven metrics the baseline needs before an overhaul, and the six steps that bring inventory down afterwards without putting the ability to deliver at risk.

Wolfgang Baldauf

Wolfgang Baldauf

Principal Consultant

In brief

The drivers of growing safety stocks (structural and regulatory, planning and process, organization), the metrics of the baseline, the comparison of actual and statistical target safety stock with a practical example, and a six-step approach from measuring to governance.

Safety stocks rarely grow through deliberate decisions, but mostly through reactions to crises, uncertainties buffered at every stage, and planning parameters that are not maintained. Anyone who wants to reduce them first needs a reliable baseline measurement.

In many pharmaceutical plants, safety stocks have been rising for years without anyone ever having decided it. Inventory grows through reactions to crises, through uncertainties that are buffered individually at every stage of the chain, and through planning parameters that were set once and never checked again. Increases are implemented quickly, reductions hardly at all. Inventory therefore rises in steps, a pattern known as the ratchet effect.

Anyone who wants to reduce this inventory without putting the ability to deliver at risk must first know what it consists of and where it comes from. An overhaul without a reliable baseline measurement at best shifts the problem and at worst leads to shortages. The sequence is therefore: measure first, then segment, then reduce step by step.

Why safety stocks keep growing

Structural and regulatory drivers

Part of the buffer is attributable to the industry. Active ingredients and excipients often come from Asia, frequently from a single supplier, and a change of supplier requires a change to the marketing authorization. Replenishment lead times are correspondingly long and variable. Customs-related issues, QC testing and QP release add to the effective lead time, and it is precisely these times that vary widely.

Then there are supply obligations. The statutory duty to ensure supply, shortage-prevention requirements and rebate contracts with contractual penalties make every shortage expensive, and an additional buffer then looks like the safe answer. Production optimization such as campaign manufacturing with long setup and cleaning times leads to large lots and long intervals between two production runs. Country-specific packs and serialization multiply the number of SKUs, and each one gets its own buffer.

If markets themselves prescribe safety stocks that have to be maintained, this forces earlier production and higher days of supply. Minimum remaining shelf life requirements, by contrast, work in the opposite direction: goods that sit in stock for too long can no longer be delivered in the end, so production tends to be later.

Planning and process drivers

The second part arises in planning itself. Flat coverage rules such as "three months for everyone" ignore that demand and lead time vary very differently from material to material. Master data is set once and never reviewed or adjusted afterwards, and the actual times then deviate from the values in the ERP system. Systematically overstated forecasts are additionally covered with safety stock, so the same uncertainty is paid for twice.

This repeats along the chain: active ingredient, bulk, finished goods, distribution warehouse and wholesale often buffer the same uncertainty each on their own. And the analysis often counts something that does not belong in it. Inventory resulting from minimum order quantities and lot sizes is cycle stock, not safety stock.

Organizational drivers

The incentives are the most persistent. A shortage is visible and escalates, while excess stock and tied-up capital stay invisible in day-to-day business. After disruptions such as the pandemic or a supply failure, buffers are raised and afterwards not taken back. Often nobody is responsible for the parameters, and in S&OP there is no fixed date at which they are reviewed.

The consequences are high capital tie-up, expiry and write-offs, full warehouses, and process problems that the inventory conceals.

What has to be measured before the overhaul

The basis is a baseline per SKU and per stage, that is, for raw material, bulk and finished goods, over 12 to 24 months. These metrics belong in it:

MetricWhat it shows
Days of supply by stageWhere the inventory actually sits and how far it is above the target days of supply
Inventory compositionShares of safety stock, cycle stock and excess stock, quarantine and obsolete goods. Only the safety stock share is the subject of the overhaul.
Service level (OTIF, fill rate, backorders)The starting level of delivery capability, against which the overhaul is measured later
Forecast quality (forecast accuracy, bias)How much demand uncertainty actually has to be covered
Replenishment lead time with variabilityMean and variance for supplier, production and QC release, often the biggest lever
Supplier reliabilityOn-time delivery and quality rejections per supplier
Production schedule adherenceWhether internal instability is driving the buffer
Expiry, write-offs, remaining shelf life profileWhat today's excess stock costs and what expiry risk follows from it
Tied-up capital and storage costsThe financial potential of the overhaul
Segmentation (ABC/XYZ, criticality)Which materials have to be treated differently, for example life-saving, single-source or shortage-prone ones
Quality lead timesTarget-actual comparison of release times for materials, intermediate and finished products

Actual versus target: where the potential lies

Two checks complement the baseline. The first concerns master data quality: do the parameters in the ERP match reality? The second is the statistical target safety stock, which can be calculated with common formulas from the service level and the variability of demand and lead time.

The gap between actual and target shows the theoretically achievable potential per SKU. Composition matters here. Cycle stock, excess stock, quarantine and obsolete goods have different causes than safety stock and need different measures. Anyone who puts them into the same number ends up reducing the wrong inventory.

How large this gap can become is shown by a project at a pharmaceutical production site: days of supply stood at 325 days. The main causes were safety stocks that had been in the system since Covid, and customer forecasts in the ERP that were far above the production capacity actually available. The inflated forecasts continuously signaled demand that did not exist in reality. Within eight months, inventory could be halved.

In six steps to lower inventory

  1. Establish the baseline. Break inventory down into its components and analyze each component.
  2. Set target service levels. By segment, agreed with Sales, Quality and Market Access. A life-saving product from a single source needs a different service level than an item with stable demand.
  3. Recalculate safety stocks. Set them statistically and test them against the history by simulation.
  4. Address the causes. Improve lead times, QC throughput, forecast bias and planning rules, instead of just lowering parameters. Anyone who only lowers the parameter has the old buffer back at the next shortage.
  5. Reduce step by step. Start with a pilot segment and monitor the service level closely.
  6. Anchor governance. Name an owner for every parameter and schedule a quarterly review in the S&OP process. Otherwise the ratchet effect starts over.

Image notice: The illustrative and header images were generated using AI and do not depict real people, places, or events. The portrait photographs show real people.

Relevant for your project?

Similar questions in your current project?

In a first call we clarify what is specifically relevant for your situation, without obligation.

Request a call →
Sources
  • Practical experience of the author in supply chain management and inventory optimization in the pharmaceutical industry

Your project

Have a concrete project?

Briefly outline your situation. We'll respond with an initial assessment, usually within one business day.

Your inquiry goes to our team, which brings in the subject-matter experts as needed.

Prefer direct? +39 02 8904 1000
contact@theentourage.it

  • Reply usually within one working day
  • 3 locations: DE · CH · IT · projects in the US too
  • 100% life sciences